• Vt.. board allows nuke plant operation through '14
    The Associated Press | March 28,2014
    • Email Article
    •  
    •  Print Article
     
    MONTPELIER - The utility-regulating Vermont Public Service Board says the Vermont Yankee nuclear plant can continue to produce electricity through the end of the year when the plant is scheduled to close.

    In a Friday ruling, the Public Service Board also approved an agreement between the state and plant owner Entergy that requires the company to pay $10 million for economic development in Windham County and to set up a $25 million fund to restore the Vernon site after the nuclear plant is decommissioned.

    Vermont Public Radio reported that the board approved a memorandum of understanding between Entergy and the state that was signed in December, ending years of legal battles.

    Vermont Yankee has been producing electricity for more than 40 years, but it will cease operations later this year.
    • Email Article
    •  
    •  Print Article
    2 Comments
    MORE IN This Just In
    VERNON – A federal appeals court has told the Shumlin administration that its challenge of a... Full Story
    Ideas about landlords, tenant rights, and the breakdown of supply and demand were tossed about in... Full Story
    Candidates for Aldermen talk issues: High rents, bad apples, drugs
    MONTPELIER — Senate lawmakers once again approved a bill requiring employers to grant their... Full Story
    More Articles