• Vt.. board allows nuke plant operation through '14
    The Associated Press | March 28,2014
    • Email Article
    •  
    •  Print Article
     
    MONTPELIER - The utility-regulating Vermont Public Service Board says the Vermont Yankee nuclear plant can continue to produce electricity through the end of the year when the plant is scheduled to close.

    In a Friday ruling, the Public Service Board also approved an agreement between the state and plant owner Entergy that requires the company to pay $10 million for economic development in Windham County and to set up a $25 million fund to restore the Vernon site after the nuclear plant is decommissioned.

    Vermont Public Radio reported that the board approved a memorandum of understanding between Entergy and the state that was signed in December, ending years of legal battles.

    Vermont Yankee has been producing electricity for more than 40 years, but it will cease operations later this year.
    • Email Article
    •  
    •  Print Article
    2 Comments
    MORE IN This Just In
    The behavior of several Rutland City Police officers named in a civil lawsuit by a former officer... Full Story
    The civil lawsuit filed against the city by a former officer alleges issues within the Rutland... Full Story
    Itís hard to get more Vermont-ish than Plymouth Notch. Full Story
    A coffeehouse festival: Plymouth Folk and Blues
    More Articles