• Castleton town hall project advances
    June 26,2013
    • Email Article
    •  
    •  Print Article
     
    Staff Report

    CASTLETON — The town hall renovation project is moving forward.

    Earlier this week an architect charged with creating a preliminary schematic design told Castleton town officials the estimated cost of the renovation of the historic brick building on Main Street was $995,329.

    This price tag came in $5,329 higher than the money the town has allocated for this project through a $750,000 bond and a $240,000 donation.

    At its meeting Monday night, town officials decided to move forward with the project using the estimates presented by John Berryhill of NBF Architects. By a 3-2 vote, the board voted to hire Berryhill to begin more concrete designs for the project to eventually take them to bid for the project.

    Berryhill said he should the design plans in about a month.
    • Email Article
    •  
    •  Print Article
    2 Comments
    MORE IN This Just In
    Colleges merger

    moves ahead

    MONTPELIER Officials are working out the details ... Full Story
    Round barn

    lost to fire

    IRASBURG A historic barn has burned to the ground in... Full Story
    JAMAICA A New York state teenager died Thursday after he slipped and fell about 100 feet at... Full Story
    More Articles