    CASTLETON — The town hall renovation project is moving forward.

    Earlier this week an architect charged with creating a preliminary schematic design told Castleton town officials the estimated cost of the renovation of the historic brick building on Main Street was $995,329.

    This price tag came in $5,329 higher than the money the town has allocated for this project through a $750,000 bond and a $240,000 donation.

    At its meeting Monday night, town officials decided to move forward with the project using the estimates presented by John Berryhill of NBF Architects. By a 3-2 vote, the board voted to hire Berryhill to begin more concrete designs for the project to eventually take them to bid for the project.

    Berryhill said he should the design plans in about a month.
    • Email Article
    •  
    •  Print Article
    2 Comments
    MORE IN This Just In
    The behavior of several Rutland City Police officers named in a civil lawsuit by a former officer... Full Story
    The civil lawsuit filed against the city by a former officer alleges issues within the Rutland... Full Story
    Itís hard to get more Vermont-ish than Plymouth Notch. Full Story
    A coffeehouse festival: Plymouth Folk and Blues
    More Articles